Direct Cost Variances and Management Control Multiple Choice Questions (MCQ) PDF Download - 1

Learn Direct Cost Variances and Management Control Multiple Choice Questions and Answers (MCQs), Direct Cost Variances and Management Control quiz answers PDF to study Cost Accounting course test 1 for online classes. Price and Efficiency Variance MCQs, Direct Cost Variances and Management Control trivia questions and answers for placement and to prepare for job interview. Direct Cost Variances and Management Control Book PDF: price and efficiency variance, use of variances career test for master's degree in business administration.

"If the actual price input is $700, the budgeted price of input is $400 and the actual quantity of input are 50 units, then the price variance will be" Multiple Choice Questions (MCQ Quiz): direct cost variances and management control App APK with $13,000, $15,000, $11,000, and $9,000 choices for online BBA degree. Practice price and efficiency variance quiz questions for jobs' assessment test and online courses for online business administration degree classes.

MCQs on Direct Cost Variances & Management Control Quiz

MCQ: If the actual price input is $700, the budgeted price of input is $400 and the actual quantity of input are 50 units, then the price variance will be

$15,000
$13,000
$11,000
$9,000

MCQ: If the actual input price is $150 and the budgeted input price is $80, then the price variance will be

$130
$70
$150
$80

MCQ: The standard input allows one unit, to be divided by standard cost per output unit, for variable direct cost input to calculate

standard price per input unit
standard price per output unit
standard cost per input unit
standard cost per output unit

MCQ: The consideration of decreased operating income relative to budgeted amount, in static budget is classified as

revenue variance
cost variance
favorable variance
unfavorable variance

MCQ: If the flexible budget variance is $105000, the actual cost is $65000 then the flexible budget cost will be

$40,000
$50,000
$150,000
$170,000

Download Free Apps

Cost Accounting App

ALL-in-ONE Courses App Download

Cost Accounting App

Cost Accounting App Download

BBA Economics App

BBA Economics App Download

Marketing Management App

Marketing Management App Download